Frosted glass installation process
- 2019-06-24-

Frosted glass installation selection, tailoring → stacking by specifications → wipe clean before device → scrape putty → mosaic glass → scrape putty, clean edge
  1. Place the glass that needs to be installed into place according to the specifications and quantity of the parts; the quantity of the distribution should be based on the number of devices on the day, and should not be excessive, so as to reduce transfer and reduction The loss of glass.
  2. The general installation order should be installed outside doors and windows first, then inside doors and windows first, and then from northwest to southeast order. If labor permits, installation can also be performed at the same time.
  3. The cutout should be cleaned before the glass installation. First, apply 1 ~ 3 mm thick putty between the bottom surface of the glass and the cut along the entire length of the cut, then push the glass flat and compact, then collect the bottom .
  4 After the glass is flattened and compacted, nails are nailed on all four sides. The distance between the nails is 150 ~ {{2}} mm, and each side should be no less than {{3 }} Nails, tap the glass with your hands after nailing, the sound is solid, indicating that the glass device is flat; if the sound beats and pulls, it shows that the putty is not strict, you need to remove the glass from the beginning, after laying the bottom putty, then push and squeeze it flat Then, fill it with putty and flatten the ash edge. If wood sticks are selected for use, dry oil should be applied first, and the glass should not be pressed too tightly.
  5. The glass of steel doors and windows is fixed with steel wire clips. The distance between the steel wire clips should not be greater than 300 mm, and there should be no less than 2 on each side. For rubber pads, the rubber pads should be embedded in the cutout first, and fixed with clamps and screws.
  6. If the glass of the inclined skylight of the device is not required by the plan, wire glass should be used, and the device should be covered in the direction of the water. The length of the overlap of the cover should depend on the slope of the skylight. When the degree is {{1} / 4 or greater than {{{1}} / 4, it is not less than 30 mm; the slope is less than {{ When 1}} / 4, it is not less than 50 mm. Use a steel card to fix the cover, and fill it with sealing paste in the gap. If you choose flat glass, you need to Add a layer of galvanized lead wire mesh under the glass.
  7 For example, if the device is colored glass and embossed glass, it should be carefully cut according to the planning drawings, and the joints must be in line, and no defects such as loosening and slanting are allowed.